Pivot Energy is an energy provider and independent power producer that develops, finances, builds, owns, and manages solar and energy storage projects. The company leverages its expertise to provide a range of unique offerings that help meet the ever-increasing demand for energy. As a leader in socially impactful and responsible solar development, Pivot ensures its projects deliver meaningful benefits to the communities in which it operates. Through all of its projects, Pivot drives positive impact through three pillars: low-cost reliable energy, property rights and land preservation, and local economic development. Pivot Energy is an ECP portfolio company. Learn more at www.pivotenergy.net.

We are developing projects to support American energy independence, provide a reliable and low-cost energy alternative, and create new local jobs and economic development.
Learn more about Pivot Energy’s approach to land stewardship and community engagement.
To ensure you are informed about what to expect during each phase, we've outlined the 10-step construction journey.
Watch the video below to see how a solar farm is constructed and what you, as a landowner, can expect.
Before any construction begins, a Pivot field member will meet with the landowner, and a representative from the local utility to review where project construction will take place. This part of the process typically takes less than a day. Individuals conducting the tour will need access to the leased area, but no heavy equipment will be present.
A ~10-person crew will build an access road for construction equipment and workers – a 1 to 2 week process that may impact traffic on nearby roads. Expect construction noise including vehicle backup beepers and cement mixers. Initial equipment mobilization takes about one day.
A 1-3 person survey team will mark lease boundaries and access points, followed by a ~5-person construction team installing permit-approved fencing. This process should take approximately 1 to 3 weeks, depending on site size and terrain, and noise levels will be similar to those of other types of agricultural/development activities.
Where necessary, grading machines will be used to clear the property of vegetative material and debris to prepare the land in compliance with the site design. This process may take between a few days to 3 weeks, and you should expect some construction sounds (e.g. tree removal/trimming, and grading equipment).
Steel posts, called piles, will be driven into the ground to support the solar panels, then fitted with racking equipment. This is typically the noisiest part of the process and takes an average of 2 to 3 weeks to complete.
Crews will install electrical equipment on concrete pads or utility poles, complete any underground work, and connect the array. This phase typically takes 1 to 2 months, with noise levels similar to panel installation (step 6).
Installation teams will clamp each solar panel onto the racking system, requiring full site access. This relatively quiet process takes 2 to 4 weeks, depending on project size, and may be combined with steps 5 and 7.
Interconnection integrates the solar project into the local electric grid. Rigorous testing is conducted to ensure all equipment meets the utility’s requirements and criteria so the project can connect to the grid. Depending on how much power the site generates, utility poles or substations may be added or modified to accommodate additional electricity. Because timeframes vary from utility to utility, this step may take anywhere from a few weeks to a few months.
Commissioning involves the testing of equipment and the installation of proper settings. This phase includes programming and quality control of the electrical components and materials previously installed onsite. This process typically takes 2 to 3 weeks of intermittent work.
The local solar project is now operational! In these final days, our team will complete the finishing touches – from establishing vegetation management to making any minor adjustments – ensuring the site is ready for decades of clean energy production. All construction equipment will be removed, leaving you with a fully functional solar facility.
After a short construction period (approximately 4-6 months), our project will create no noise, have no onsite employees, and generate no emissions or traffic in the area.
Learn more about what to expect during construction and how solar projects support local farmers and communities through the resources below.
Give us a call at (888) 734-3033, we're happy to answer all of your questions, and address any concerns.
We would love to hear from you.
Fill out the form to provide us with your information and a local Pivot representative will be in touch with a free property analysis.